A quick view on the progress to date at GinGin. This strings together a few different visits, getting us from an earmarked area, to concrete pad, storage unit, reticulated network install and steel structure for the plant fully erected.

We expect the next update to be when the gantry is in place (for our fine screen) and the plant building (walls & roofing) are in place.

From that point onward - the focus will be on the actual plant build and commissioning.